Rebuild existing 34kV to 69kV standards, including but not limited to: install conductors, overhead shield wires (OHSW), fiber optic ground wire (OPGW) and All Dielectric Self-Supporting Fiber Optic Cable (ADSS). The scope of work includes the pulling, splicing and testing of underground ADSS into the remote end substations via existing underground conduits and inner-duct. In total, 30 structures were replaced along a span of approximately two-miles, in a sensitive wetlands environment. Also completed was the installation of 4,000 timber mats and 2,000 feet of erosion control filter sock to protect the wetlands and surrounding environment.

Portrait of Section 105 Rebuild - Old Orchard Beach, Maine

Thomas Halpin

Vice President

Mark Grimes

Project Manager

Jeff Mador

Superintendent

Section 105 Rebuild - Old Orchard Beach, Maine

PROJECT COMPLETED

2

MONTHS