We rebuilt approximately two miles of transmission line, while the existing 35kV line remained energized. Haugland crews installed a 21 new structures, single pole, H-Frame and 3-pole dead ends. A new feeder was built around the existing substation, and the wire on the right-of-way was transferred, using the 35kV gloving method. New conductors were installed on a 1000-foot span river crossing, which included coordinating boat traffic State authorities.

Portrait of PSNH Line 3750 Partial Rebuild

Thomas Halpin

Vice President

Mike Repetti

Project Manager

Casey Gillespie

Superintendent

Tobey Whitney

Safety Manager

PSNH Line 3750 Partial Rebuild

PROJECT COMPLETED

4

MONTHS