This project included the removal and installation of two 115kV transmission through wetlands and ledge conditions. Construction of 6.4 miles circuit miles of conductor, OPGW and H-Frame wood structures were completed at 75 locations. Our environmental crews, led by our in-house erosion control specialist, managed and installed 7,000 timber matts, and cleared three miles of right-of-way, then installed environmental controls throughout the right-of-way.

Portrait of Norwood 115kV Transmission Line Replacement

Thomas Halpin

Vice President

Mark Grimes

Project Manager

Casey Gillespie

Superintendent

Tobey Whitney

Safety Manager

Norwood 115kV Transmission Line Replacement

PROJECT COMPLETED

8

MONTHS