This project for WMGL required the installation of 15kV Hendrix spacer cable, along with new secondary cable, the transfer/replacement of existing equipment, and the replacement of 60 guyed and un-guyed wooden poles. During the phased demolition, the existing circuit needed to remain energized, and customer outages were prohibited.