U.S. Virgin Islands Storm Restoration

U.S. Virgin Islands Storm Restoration

Virgin Islands Water and Power Authority (WAPA)

The Virgin Islands Water and Power Authority contracted Haugland Energy to provide emergency line crews and equipment for the restoration of electrical transmission and distribution systems after Hurricanes Irma and Maria devastated the area in late summer/early fall 2017.

Project Details

FEMA Long Island Electric Distribution Storm Hardening

FEMA Long Island Electric Distribution Storm Hardening

PSEG Long Island

This $200+ million, three-year reliability and resiliency project will further strengthen the electric grid across Long Island and in the Rockaways. Following Superstorm Sandy, LIPA and National Grid (the previous service provider to LIPA) acquired funds under the FEMA 406 Mitigation program to implement a Hazard Mitigation Program to the LIPA transmission and distribution system. The primary focus of the program is to harden Long Isl​and's Transmission and Distribution system by upgrading approximately 450 miles of mainline distribution lines. This is an effort to increase resilience to future storm damage, and reduce the number of customers impacted by service interruptions by 20% when storm damage occurs.

Project Details

Rockaway Boardwalk Reconstruction

Rockaway Boardwalk Reconstruction

Rockaway, New York

To date, Grace Industries has been awarded 19 contracts at the Rockaway Boardwalk project, spread out over five phases. The 4.7-mile project includes the installation of more durable structures and dunes at beaches, boardwalks, and adjacent DPR property lines; bolstering efforts to prevent future damage from storms like Superstorm Sandy.

Project Details

Long Beach Boardwalk Reconstruction

Long Beach Boardwalk Reconstruction

City of Long Beach

The scope of this $44 million project called for the reconstruction of the iconic Long Beach Boardwalk. The 2.2 mile long boardwalk was destroyed by Superstorm Sandy. This 200-day fast tracked project is on time and on budget.

Project Details

City of Long Beach Comfort Stations

City of Long Beach Comfort Stations

City of Long Beach, NY

Grace Industries constructed five elevated Comfort Stations along the Long Beach Boardwalk, replacing the existing bathrooms which were heavily damaged during Superstorm Sandy. Work included construction of pile supported, cast-in-place concrete foundations. The prefabricated concrete unit bathroom structures were assembled using a crane at each location.

Project Details

NCDPW Bay Park Sewage Treatment Plant Perimeter Flood Protection Berm & Wall

NCDPW Bay Park Sewage Treatment Plant Perimeter Flood Protection Berm & Wall

NCDPW

Grace Industries was contracted to construct a 6,700 linear foot flood wall around the Bay Park Sewage Treatment Plant in East Rockaway, New York to protect against storms like Superstorm Sandy. The wall consists of a subterranean slurry wall extending 25 feet below sea level, as well as a combination of concrete walls and earthen levee berms that reach 17 feet above sea level.